Samsung HI and others face USD33 million penalty for delayed LNG ships

Delays in the production of membrane tanks for two of six LNG carriers being built for SK Shipping to service long-term shipping contracts with Korea Gas Corporation has caused the vessel deliveries to be pushed back by six months to February and March 2018.